Nagpur Metro has launched its first 31-meter span in Reach-4A of Phase-II (Prajapati Nagar–Transport Nagar, 5.31 km). This marks the start of segment erection, boosting connectivity to industries, universities, and markets. With advanced engineering, strict safety measures, and a unique double-decker section, the project moves closer to transforming urban mobility.
Introduction:
Nagpur Metro continues to accelerate progress under its Phase-II development. In a significant achievement, the project has successfully launched the first 31-meter span in the Reach-4A section, which stretches 5.31 km from Prajapati Nagar to Transport Nagar. This milestone marks the beginning of segment erection on this corridor, bringing Nagpur closer to a modern, efficient, and sustainable public transport system.
Construction Milestone:
The launch involved assembling 11 precast segments to form the first span. Advanced materials and equipment were deployed:
- 180 m³ of M50 grade concrete and 28.5 tons of Fe550D steel were used to ensure structural strength.
- A 220-ton crane facilitated the erection, with strict adherence to safety standards.
- A 2 km double-decker viaduct portion within this section makes the project a unique feature in the region.
This engineering achievement demonstrates the scale, complexity, and precision required in metro construction.
Connectivity Boost:
The Reach-4A corridor plays a crucial role in improving connectivity. Once completed, it will connect multiple key hubs, including:
- Bhandara Road industries
- Kalamna Market
- Symbiosis University
- Hingna and Butibori industrial belts
- Kanhan and adjoining areas
The alignment is designed to serve both industrial zones and educational hubs, thereby catering to a diverse group of commuters.
Progress Across Phase-II:
The Phase-II expansion of Nagpur Metro includes multiple corridors under active construction. Segment erection is already in full swing across several stretches. With the addition of Reach-4A to the list of actively progressing sections, Phase-II is on track to significantly enhance the city’s transport infrastructure.
Key Highlights:
- Span Size: 31 meters
- Segments Used: 11
- Materials: 180 m³ M50 grade concrete, 28.5 tons Fe550D steel
- Equipment: 220-ton crane with safety measures
- Unique Feature: 2 km double-decker viaduct
These highlights underline the blend of technology, safety, and planning that defines Nagpur Metro’s ongoing construction.
Towards a Greener Future:
Beyond connectivity, the project emphasizes sustainability. By offering an alternative to road transport, Nagpur Metro aims to reduce congestion, minimize vehicular emissions, and contribute to a greener urban environment. Phase-II aligns with the broader vision of smart city development and eco-friendly transport solutions.
Conclusion:
The successful launch of the first span in Reach-4A symbolizes steady progress in Nagpur Metro’s Phase-II. With advanced engineering, enhanced connectivity, and sustainability at its core, the project is shaping Nagpur’s transformation into a modern, smarter, and greener city while meeting the growing mobility demands of its citizens.
Source: Nagpur Metro | Image Credit: Nagpur Metro
[Nominations are Open] Submit your nomination (free) for the 7th Rail & Metro Awards 2026: Link
Timely insights, straight to your WhatsApp—stay updated with ease!
Stay connected to the rail industry—timely news, straight to Telegram!