The Mumbai Metro Rail Corporation Limited (MMRC) has completed 100% track laying on both the up and down lines of the Mumbai Metro Line 3 corridor from Aarey to Cuffe Parade. This milestone signifies steady progress in commissioning the 33.5-km-long Colaba-Bandra-SEEPZ metro corridor, set to transform Mumbai’s urban transit system.
Introduction:
Mumbai Metro Line 3, also known as the Aqua Line, is a 33.5-km-long corridor designed to ease traffic congestion in Greater Mumbai. The project aims to enhance connectivity across Colaba, Bandra, and SEEPZ. As part of its phased implementation, progress on Phase 2 from BKC to Cuffe Parade includes:
- Station and Tunnel Works: 99.1% completed
- Overall Station Construction: 97.6% completed
- Overall Systems Works: 58.7% completed
- Mainline Track Works: 99.1% completed
- OCS Works: 57.1% completed
About Mumbai Metro Line 3:
MML-3 is one of Mumbai’s most ambitious infrastructure projects, aimed at improving urban transportation in India’s financial capital. With a fully underground network, the project connects major business districts and residential areas, ensuring a seamless travel experience for millions of commuters.
Significance of Completion:
The completion of track laying signals that the project is on track for full commissioning. This milestone brings the city closer to a sustainable, efficient, and modern metro system, which will alleviate traffic congestion and provide an environmentally friendly mode of transportation.
Conclusion:
The completion of track laying on Mumbai Metro Line 3 reflects MMRC’s dedication to enhancing Mumbai’s public transport infrastructure. As the project nears commissioning, MML-3 is set to transform urban mobility, offering faster and greener connectivity to Mumbai’s residents while addressing the city’s growing traffic challenges.