Nagpur metro Phase-2: Tender released for elevated viaducts construction

  • The Design and Build Contractor has to design the Viaduct ensuring a minimum statutory vertical clearance of 5.5 metres to the Metro structure above the existing road level. Sectional elevation of the typical elevated viaduct drawing enclosed with the tender/bid documents shall be referred for the same.
  • Whole length of the viaduct has to be designed for double line standard gauge track as shown in the GAD. System is planned with end evacuation and 25 KV AC OHE traction. The tenderer/bidder will have to use a Segmental Box girder integrated with the parapet (Segmental box girder is Maha-Metro’s preferred choice).
  • Some spans will have to be designed to accommodate the emergency track crossover, special track layouts (e.g. pocket track) (Approximate locations if any are shown in the GAD for reference).
  • One Similar completed Work costing not less than the amount equal to Rs. 808 Crores; or
  • Two Similar completed Works each costing not less than the amount equal to Rs. 505 Crores; or
  • Three Similar completed Works each costing not less than the amount equal to Rs. 404 Crores.